EBENE, Mauritius--(BUSINESS WIRE)--
Azure Power Global Limited (NYSE: AZRE), (“Azure Power” or “the
Company”), one of the leaders in the Indian solar industry, today
announced its consolidated results under United States Generally
Accepted Accounting Principles (US GAAP) for the fiscal fourth quarter
2017, period ended March 31, 2017.
Fourth Quarter 2017 Period Ended March 31, 2017 Operating Highlights:
-
Operating & Committed Megawatts were 1,069 MW, as of March 31, 2017,
an increase of 31% over March 31, 2016.
-
Revenue for the quarter was INR 1,318 million (US$ 20.3 million), an
increase of 72% over the quarter ended March 31, 2016.
-
Adjusted EBITDA for the quarter was INR 974 million (US$ 15.0
million), an increase of 90% over the quarter ended March 31, 2016.
Key Operating and Financial Metrics:
Electricity generation during the fiscal year ended March 31, 2017
increased by 252.7 million kWh, or 69%, to 617.5 million kWh, compared
to the same period in 2016. The increase in electricity generation was
principally a result of additional capacity operating during the period.
Total revenue during fiscal year ended March 31, 2017 was INR 4,183.0
million (US$ 64.5 million), up 59% from INR 2,626.1 million during the
same period in 2016. The increase in revenue was primarily driven by the
commissioning of new projects.
Project cost per megawatt operating consists of costs incurred for one
megawatt of new solar power plant capacity during the reporting period.
The project cost per megawatt operating for the fiscal year ended March
31, 2017 decreased by INR 10.3 million (US$ 0.16 million) to INR 49.3
million (US$ 0.76 million), as compared to the same period in 2016. The
decline is due to decreasing solar module prices and the reduction in
balance of system costs.
As of March 31, 2017, our operating and committed megawatts increased by
254 MW to 1,069 MW compared to March 31, 2016 as a result of winning new
projects. In Feb 2017, WTO ruled against India’s Domestic Content
Requirement for solar projects. Solar Energy Corporation of India (SECI)
cancelled private procurements with domestic content requirements and
did not sign a 50 MW contract (Andhra Pradesh 4) with Azure Power which
had a domestic content requirement. The Company did not incur any
significant costs related to Andhra Pradesh 4.
Click here to view the full press release